November 2026 Campus Construction Updates
Progress continues across campus as key projects advance. Here’s a snapshot of what’s taking shape on Bison Hill this month.
Raley Chapel

Work continues throughout Raley Chapel and the surrounding construction site as several major elements of the project take shape.
On the east side of the site, the pavers on the bridge have been installed and veneering of the sides is underway. A solution for stormwater drainage at Kerr Parking Lot is currently under design to prevent potential flooding in this area. On the west side, final grading and sod are complete, and the western portion of the Ichthus sidewalk that was left open for access is now paved.
The most visible progress is on the north side of Raley Chapel, where the new Raley Rotunda is being constructed. The structural steel and footings are now complete. The monument will host a sculptural piece in the center beneath the oculus (an opening at the top of the dome) and will honor more than a century of collaboration among OBU, the City of Shawnee and Pottawatomie County coming together to meet challenges and move forward as one community.
Construction is also underway on the walls for the new monument sign marking the north entrance to campus, along with the final portions of the Ichthus sidewalks. Irrigation is nearing completion, with final grading and sod work upcoming.

In the basement, ductwork insulation, hydronic piping and conduit installation continue. The space for the organ blower is being prepared for the blower to be lowered back into place and reinstalled, while ductwork for the organ is being installed on the first floor.
Elsewhere on the first floor, overhead rough-in for mechanical, electrical and plumbing systems continues. HVAC insulation and grilles are being installed, along with elevator pit sump pumps.
In the east wing of the second floor, work continues on the elevator shaft walls, while bathroom fixtures and finishes are being installed. Across both wings of the second floor, millwork, window sills and trim work are upcoming.
In the lobby of Potter Auditorium, taping, bedding and priming are underway in both stairwells, and wall tile is being installed in the bathrooms. Structural steel work for the stained-glass windows is also underway.
Inside Potter Auditorium, the original stage has been demolished and structural steel for the new stage is now being installed. Steel window reinforcements are nearing completion. Framing for walls and ceilings is underway, with electrical rough-in upcoming.
Stained Glass

Reinstallation of the historic stained glass is underway. Inside, the windows are being covered with plywood as they are installed. This plywood covering will remain for the next few months as construction continues inside. On the exterior, the protective glass has been installed on the west side. That process will continue on the other windows around the exterior. That protective glass protects the stained glass from dirt, debris and potential storms. To be a part of the stained glass restoration, visit okbu.edu/giving/shape-the-future/raley-chapel and click on “Give Now.”
Geiger Center

Sidewalks are complete, and grading and sod have been completed around the loading dock on the north side of the Geiger Center. Fence installation is upcoming, along with bollards and additional concrete work at Sarkeys.
Noble Complex
Updates to the back-of-house spaces in the Noble Complex are underway. Painting of the west hallway is complete, and demolition of the tile flooring is underway.
The work will extend into the hallways serving the basketball offices and locker rooms, where a new epoxy floor will be installed to match the flooring in the athletic training office. Final stages of the project are expected to be completed after the first of the year.